Commercial · Project profile

Barron’s Branch District

By Elena Castillo

City of Waco · Waco

$190.414M current district budget · $55M filed park scope · 30 acresDistrict under construction · park phase filedUpdates Every Monday
Barron’s Branch District concept rendering with creek and public spaces
District concept rendering: City of Waco and Hunt Development Group.

Waco’s downtown public works and park program is underway. A $55M park registration targets August 2028; the current overall district target is March 31, 2029.

Project overview

Waco’s approximately 30-acre Barron’s Branch District is under construction following its September 24, 2026 groundbreaking. Hunt Real Estate & Infrastructure is master developer and Rogers-O’Brien Construction is general contractor. The program renews streets, utilities and drainage while restoring the creek corridor and creating public parks and plazas.

The city’s current project page lists a total district budget of $190,414,000 and completion on March 31, 2029. The earlier Master Development Agreement was described at approximately $184 million. A separate November 18 park filing records $55 million for 350,638 SF, around eight acres, with an April 2027–August 2028 schedule. These figures describe overlapping scopes and must not be added together.

Public works are intended to enable more than $800 million in later private investment. That is a development projection, with individual private buildings subject to separate decisions, procurement and schedules.

Latest updates

Construction timeline, from announcement through delivery. Filed dates and future targets are labeled separately from confirmed events. Reviewed November 19, 2026.

  1. 2025

    Design and Funding Preparation

    Waco’s annual report records completion of the draft form-based code and establishment of the first-phase funding model. This planning work preceded the district’s construction program.

  2. February 5, 2026

    Development Proposals Requested

    The city and Hunt issued the Barron’s Branch District developer request for proposals. This private-development procurement is distinct from the subsequent public infrastructure construction contract.

  3. September 24, 2026

    Confirmed milestone

    District groundbreaking

    The City of Waco, Hunt and Rogers-O’Brien mark the groundbreaking for the downtown district.

  4. September 29, 2026

    Construction update

    Construction start formally announced

    The city announces the approximately $184M public-improvement program, beginning with streets and underground utilities ahead of park construction.

  5. November 18, 2026

    State registration

    $55 million park phase registered

    The city registered 350,638 SF of public park work under TABS 2027006181. Michael Van Valkenburgh Associates is the listed design firm. The owner-estimated schedule is April 1, 2027–August 18, 2028, separate from the ongoing district infrastructure works.

  6. November 19, 2026

    Current project record

    Current district budget and delivery target reviewed

    The city’s project page lists a $190.414 million total budget and March 31, 2029 completion. The September announcement’s approximately $184 million agreement and April 2029 forecast remain historical context; this review date is not a new council approval date.

  7. August 18, 2028

    Target

    Filed park completion target

    Estimated finish for the registered park scope, ahead of overall district completion.

  8. March 31, 2029

    Target

    Overall district completion target

    Current city project-page target for public improvements; private development has separate schedules.

Rebuilding the district from below ground

The first work concentrates on the infrastructure needed to support the district: roads, replacement underground services, drainage and reconstruction of Barron’s Branch Creek. Some of the infrastructure being replaced is around 80 years old, making renewal of existing systems a central part of the undertaking.

Parks and plazas are also included. The project combines the practical work of servicing future development sites with the creation of public spaces that will shape how the district is used. It is a district-scale civil and public-realm program rather than a single vertical building project.

A multidisciplinary delivery team

Hunt Real Estate & Infrastructure is the master developer, with Rogers-O’Brien leading construction. Michael Van Valkenburgh Associates is responsible for landscape and master-planning leadership, Walker Partners for civil engineering and Overland Partners for architecture.

TYLin is identified for structural engineering and Schlaich Bergermann Partner for bridge engineering. Domingo Gonzalez Associates is the lighting consultant, while EEA Consulting Engineers provides mechanical, electrical and plumbing expertise.

The specialist team also includes Terracon for geostructures, GPSI for water features and WC3 Design for irrigation. The range of appointments reflects a scope that joins underground infrastructure, creek works, structures, landscape and public-space systems.

Public works intended to unlock private development

The approximately $184 million agreement covers the public development program. The separate estimate of more than $800 million in potential private investment describes what those improvements could help unlock over time; it should not be combined with the agreement as a single awarded construction contract.

Road access, drainage and utilities are enabling works for later development. Completing them establishes the physical foundation for subsequent investment, while the timing and form of individual private projects will depend on their own development decisions.

Park delivery and district completion

The park registration targets work from April 2027 to August 2028. The city’s current overall district schedule ends March 31, 2029, superseding the April 2029 forecast used in the September announcement.

The design includes creekside paths, fountains and water play, a performance pavilion, pedestrian connections and Calle Dos public spaces. Ongoing underground infrastructure and street renewal enable those improvements and later private buildings.

Rogers-O’Brien’s June 2026 subcontract bid deadline is a historical procurement milestone. Current package availability requires confirmation with the construction team; it should not be presented as an open tender.

What to watch next

  • Progress of district utility, drainage and street works.
  • Verified park mobilization against the April 2027 filed start.
  • Park completion against August 2028 and overall public works against March 2029 targets.
  • Separate awards and delivery schedules for later private development.
Read the $55 million park filing ↗