Texas Department of Transportation · Southwest Austin
$677M · approximately seven milesCompletedUpdated September 29, 2026
Opening ceremony: Fluor.
Explore the completed roadway, delivery team and construction timeline in this free Project Insight. Final paving, striping and landscaping continue through late 2026.
Project overview
Oak Hill Parkway is a $677 million reconstruction of approximately seven miles of U.S. 290 and SH 71 in southwest Austin. The main roadway system is now open following a September 24, 2026 opening ceremony.
Colorado River Constructors, the Fluor and Balfour Beatty joint venture, delivered the design-build project for the Texas Department of Transportation, with AECOM as lead designer. Construction began in 2021.
The project is marked completed for the opening of its main roadway system. Final paving, striping and landscaping continue through the end of 2026.
Latest updates
Construction timeline, from announcement through delivery. Filed dates and future targets are labeled separately from confirmed events. Reviewed September 29, 2026.
2021
Construction milestone
Construction begins
Work starts on the U.S. 290 and SH 71 corridor reconstruction.
2025
Progress report
Major construction progress
Fluor’s progress report records more than four million work hours and major drainage, utility, pavement and bridge work.
September 24, 2026
Completed — main roadway
Opening ceremony
The project team and TxDOT mark the opening of the main roadway system.
September 25, 2026
Company announcement
Opening announced by Fluor
Fluor confirms the opening milestone and the remaining finishing works.
End of 2026 target
Target
Remaining finishing work
Final paving, pavement markings and landscaping are scheduled to continue through year-end.
Project team
Owner: Texas Department of Transportation (TxDOT)
Design Build Contractor: Colorado River Constructors
Joint venture partners: Fluor and Balfour Beatty
Lead designer: AECOM
Project scope
The design-build scope combines highway capacity, new structures and connections for local traffic, pedestrians and cyclists:
Approximately seven miles of improvements to U.S. 290 and SH 71
Main lanes widened from two to three in each direction
New flyovers and overpasses
New frontage roads
Shared-use pedestrian and bicycle infrastructure
Replacement of the former Y-interchange with a single-point urban interchange
The construction behind the new roadway
The scale of the work extends well below and beyond the travel lanes. In a 2025 progress report, Fluor recorded more than four million work hours, over 150,000 linear feet of underground drainage and utilities, and more than 750,000 square feet of bridge decks. Those figures describe an earlier construction snapshot rather than final quantities at opening.
The same report identified almost 200,000 square yards of concrete pavement. At peak activity, approximately 600 craft workers and subcontractor personnel supported delivery. Keeping a major regional route functioning while replacing its structures, drainage and junctions made sequencing central to the job.
Paths, drainage and material reuse
The scheme also includes 14 miles of shared-use paths and approximately 1.5 miles of sidewalks. These connections make the corridor improvements relevant to people walking and cycling as well as drivers. Stormwater detention and water-quality ponds form another part of the infrastructure package.
Fluor described an on-site recycling approach that reused existing roadway material in cement-treated base. Its progress report put reclaimed material at roughly 95% of that base mix, with about 125,000 tons of recycled base produced. Reusing material within the project reduced the need to treat all demolished pavement as waste.
Work remaining after opening
Opening the roadway does not mean every construction activity has ended. Final paving, pavement markings and landscaping are scheduled to continue through the end of 2026. Drivers should continue to watch for work zones as the contractor completes those remaining elements.
Explore other projects
Image: Tesla / SpaceX — Terafab project visualization
Fermi America’s planned 17GW power and data-center campus in the Panhandle, described by the developer as the world’s largest private power and compute campus.
Read project insight Concept illustration — not the actual campus design or a site photograph.
A campus spanning more than 1,100 acres between Valley International Airport and the Port of Harlingen. Members can explore the Phase 1 scope, reported project team and construction timeline.
A multiyear transformation of Houston’s convention campus and surrounding district. GRB South targets a May 2028 opening, with the full transformation anticipated by 2038. Members can explore the development team, construction packages and timeline.
8 buildings · approximately 4M SF · 1.2 GW planned
Abilene is the flagship campus associated with the $500 billion national Stargate initiative. The eight-building core combines data halls, cooling and power infrastructure. Explore the project team, construction packages and full delivery timeline in this free Project Insight.
A research and teaching facility on West Campus combining laboratories, processing spaces and public-facing facilities. Members can explore the delivery team, utility package and construction timeline.
A specialist research and training facility with cleanrooms, advanced laboratories and major supporting utilities. Explore the complete project team and delivery schedule in this free Project Insight.
The completed 75,000-SF first phase includes three buildings and supporting infrastructure within TIG Real Estate Services’ planned 41-acre business park.
Crossland is delivering the 1,007,817-SF first building at Intermodal Logistics Center West, with CBRE marketing Q1 2027 delivery within the planned $750 million campus.
Read project insight Image: City of Waco / Waco Downtown Redevelopment. District rendering.
The 30-acre downtown district is moving into construction under Hunt Real Estate & Infrastructure, with roads, utilities, public spaces and creek reconstruction targeted for completion in April 2029.
850,000 SF announced · up to 40GW annual production
Freehill’s Fairbanks Landing Phase I adds developer and design-team detail to Power Electronics’ Houston campus, planned for up to 40GW of annual production capacity.
Read project insight Rendering: Austin-Bergstrom International Airport / City of Austin.
$22.3B · 6.47GW generation · 5GW adjacent data campus
Track the development partners, permitting milestones and phased delivery of the proposed Encinal power campus serving an adjacent digital infrastructure development.
$3B+ · 835-acre initial site · 1.2M SF enclosed production
An initial 835-acre shipbuilding campus at the Port of Brownsville with production buildings, deepwater quay and room for future expansion. Members can explore the construction team and delivery milestones.
A manufacturing campus on Palo Alto Road planned for telehandlers, scissor lifts and aerial-access equipment. Members can explore the delivery team, construction scope and phased handover schedule.
A West Dallas data-center development with separate core-building and interior fit-out packages. Members can explore the contractor map, construction scope and filed delivery timeline.
A two-phase renewal of courts, recreation buildings, trails and public spaces at the historic Third Ward park. Members can explore the delivery team and construction timeline.
A new secure state facility in Rosharon, paired with a separate Ellis County development. Members can explore the project team, shared funding context and dated construction milestones.
Read project insight Hutto campus photograph supplied by the publisher; existing campus buildings, not the proposed Building 4.
160-acre marketed campus · $550M Building 4 filing
A phased Skybox–Prologis data-center campus in Hutto. Members can explore the campus contractor, building-specific scope, power-capacity distinctions and delivery timeline.
The construction story behind the Cowboys’ home: its original delivery team, retractable roof, mechanical systems and long-term reinvestment. Full profile free to read.
Read project insight Image supplied by publisher; photograph shows the stadium under its former NRG name.
Explore the Texans’ stadium from its 2000 groundbreaking to its original contractor team, cooling systems and later roof renewal. Full profile free to read.