CHRISTUS Spohn Sets $14 Million Envelope and Site Work Around Shoreline Demolition

CHRISTUS Spohn Hospital Corpus Christi–Shoreline
Existing Shoreline campus. Photo: CHRISTUS Health.

The 30-month job at 600 and 608 Elizabeth St. in Corpus Christi covers 35,000 square feet of work before and after a demolition, designed by CLK Architects & Associates.

CHRISTUS Spohn Health System plans $14 million of exterior envelope and site work at CHRISTUS Spohn Hospital Shoreline, 600 and 608 Elizabeth St., Corpus Christi, Nueces County, according to a state filing registered Nov. 19, 2026. The filing covers 35,000 square feet of pre-demolition construction work, followed by post-demolition construction of an exterior envelope and miscellaneous site work.

The filing lists an estimated cost of $14,035,000, with work running from Dec. 14, 2026, to June 1, 2029, about 30 months. The project is privately funded. An exterior envelope is the outer shell of a building, its walls, windows and roof, which seals it from the weather. The filing does not say which structure will be demolished.

Shoreline is the system's main hospital in Corpus Christi. CHRISTUS describes it as the region's largest acute care facility and a Level II trauma center serving the Coastal Bend, as well as a Level I stroke center. It is a teaching hospital affiliated with the Texas A&M University System Health and Science Center College of Medicine. Its Pavilion and Critical Care Center house the emergency department, intensive care unit, cardiac catheterization lab and surgical suites.