Fermi Confirms Funding Under $200 Million Prepayment Agreement as Texas Tech Deadline Nears

Project Matador concept rendering

Fermi still needs a notice to proceed from the Texas Tech University System by Dec. 31, which depends on a signed tenant lease of at least 200 megawatts.

Fermi Inc. said in a November 23, 2026 SEC filing that obligations under its previously discussed customer prepayment agreement had been fulfilled and the amounts due had reached the company. Fermi had described that agreement as a $200 million commitment in its November 12 results. The new filing does not independently restate the amount or identify the customer.

The filing did not announce a signed lease, and that is the next hurdle. Under its 99-year ground lease with the Texas Tech University System, Fermi must receive a notice to proceed from the university system by Dec. 31, 2026, according to its quarterly report filed Nov. 12. If the notice is not received by that date and no extension is obtained, Texas Tech may terminate the lease. Fermi said vertical construction of data center facilities is expected to begin only after it closes a definitive tenant lease and receives the notice.

Among the conditions for that notice is a lease with a first-phase tenant for at least 200 megawatts of capacity at Project Matador. Fermi's prepayment came alongside a nonbinding letter of intent with an investment-grade hyperscaler, a large cloud computing company, for about 600 megawatts. Fermi has not named the customer. The company said the letter is subject to negotiation and signing of final documents, and that a definitive lease may never be signed.