TxDOT Plans Continuous Flow Intersection at FM 973 and US 79 in Taylor

Texas Department of Transportation logo

The proposal is part of a plan to widen FM 973 to a six-lane boulevard between US 79 and Samsung Highway. Funding and the construction schedule remain to be resolved.

The Texas Department of Transportation is proposing a continuous flow intersection at FM 973 and US 79 in Taylor as part of a larger plan to widen FM 973 between US 79 and Samsung Highway.

TxDOT held an in-person informational meeting on the intersection from 5 to 7 p.m. Thursday, Nov. 12, at the Dickey-Givens Community Center, 1015 E. MLK Jr. Blvd. in Taylor. The meeting was held in an open-house format, with attendees able to arrive at any time during the two-hour window. Meeting materials include a fact sheet, exhibit boards and schematics.

Corridor widening

TxDOT and the Capital Area Metropolitan Planning Organization are evaluating improvements along the FM 973 corridor from US 79 in Taylor to Samsung Highway in Williamson County. The project, identified as CSJ 2295-01-021, would widen the existing two- to three-lane road to a six-lane boulevard, with three lanes in each direction and a raised center median, within the existing right of way. The continuous flow intersection at US 79 is included in the proposal.

According to project documentation released by CAMPO, the proposed design also includes a new traffic signal and intersection improvements at Wesley Miller Lane, with dedicated ADA ramps and crosswalks; right-in, right-out access at Rodgers Drive, Kyra Lane, Blazilmar Lane and Reagor Drive; a 10-foot shared-use path on the east side of FM 973 and a sidewalk on the west side; and dual left-turn lanes under evaluation at the US 79 intersection for northbound and westbound traffic.

Traffic growth

Average daily traffic on the corridor was 16,400 vehicles per day in 2023 and is projected to reach 58,100 vehicles per day by 2050, an increase of about 255%, according to the corridor fact sheet. Williamson County's population was about 609,000 in 2020 and is projected to reach 1.7 million by 2050.

The study analyzed current and projected traffic volumes, existing and future land use, crash hotspots, environmental features, and stakeholder and public concerns. The project team evaluated crash data from 2018 through 2022.

Schedule and funding

TxDOT’s 2026 Unified Transportation Program lists an estimated $101,957,686 construction cost for CSJ 2295-01-021, with $61,957,686 in funding and $40 million remaining to be funded. Earlier corridor materials anticipated a 2028 construction start and about three years of work, but the UTP places letting in its fiscal 2030–2035 period. Those planning records differ, so a firm construction start or opening date has not been established.

Public input

CAMPO and TxDOT held an in-person open house on the corridor on Aug. 21, 2025, with an online open house and comment period. About 50 people attended in person, and the online open house drew 117 unique visitors. The agencies received comments from 63 commenters.

Comment themes included access for the Avery Glen and Castlewood neighborhoods and concerns that raised medians would force U-turns; requests for additional traffic signals at Avery Glen, Samsung Highway and the high school; questions about whether three lanes in each direction is excessive; and requests for a study of the southern portion of FM 973.

That southern study, covering FM 973 from Samsung Highway to US 290 in Manor, is underway. Traffic on that segment averaged 20,750 vehicles per day in 2024 and is projected to reach 84,700 vehicles per day by 2050. CAMPO and TxDOT plan to share proposed improvements for that segment in fall 2026 and refine them in 2027.

TxDOT is conducting the environmental review for the project under 23 U.S.C. 327 and a memorandum of understanding with the Federal Highway Administration dated Feb. 20, 2026.