$653 Million of I-10 and US 69 Work Advances in Jefferson County

Williams Brothers Construction and Zurich are rebuilding the Cardinal interchange, widening I-10 toward Hamshire and turning the US 69 and SH 73 cloverleaf into a turbine.
The Texas Department of Transportation's Beaumont District has four major I-10 and US 69 contracts worth a combined $653.3 million under way in Jefferson County, according to its Nov. 20, 2026, project update. Williams Brothers Construction holds three of them, and Zurich holds the fourth. The contracts rebuild the southern I-10 and US 69 interchange, widen I-10 west of Beaumont and replace a cloverleaf at US 69 and SH 73.
The largest is the $315.4 million I-10 Cardinal Interchange Widening and Reconstruction Project, from CR 131 (Walden Road) to US 90. Williams Brothers is rebuilding the southern I-10 and US 69 interchange and widening I-10 from four to six lanes, with completion set for spring 2031. Crews are building bridge columns and caps, installing drill shafts in the median, removing bridge shoulders, excavating near the BNSF crossing and building a retaining wall along Washington Boulevard.
West of Beaumont, two contracts widen I-10 from four to six lanes with new lanes and bridges. Zurich holds the $136.5 million section from FM 365 to CR 131, where crews are paving the center median, preparing concrete riprap at the Boyt Road overpass and treating soil with lime west of Kidd Gully. The Kidd Gully bridge has been demolished, and drill shafts for its replacement are being prepared. Williams Brothers holds the $119.9 million section from 0.64 mile west of Hamshire Road to FM 365, with grading west of North Fork Taylors Bayou and pile, rebar and abutment work at the FM 365 overpass. Both sections are due in spring 2028.
Checking your membership…
Explore Project Insights
Follow this project’s updates, construction milestones and researched contractor information in its dedicated Project Insight. Explore the profile for deeper coverage and membership access.
Explore project insights →