Latham & Watkins Plans $7.7 Million Office Build-Out as Houston Footprint Tops 100,000 SF

Houston and Gulf Coast regional reference; not the project site

Gensler is designing the full-floor interior on Level 34 of the 811 Main tower, with work set to run from January to August 2027.

Latham & Watkins LLP plans a $7.7 million renovation of Level 34 at 811 Main St. in downtown Houston, according to a state filing registered Nov. 19, 2026. The project is a full-floor interior build-out of office space covering 26,991 square feet, with new non-load-bearing partitions, finishes and ceilings, plus HVAC, electrical and plumbing work.

The filing lists a construction start of Jan. 11, 2027, and completion on Aug. 23, 2027, a schedule of about seven months. The work is classed as a renovation and alteration with no change in occupancy, and it is privately funded. Both dates are targets.

The new floor follows a lease expansion announced on June 1, 2026. The building's leasing team at Transwestern said Latham & Watkins added 26,763 square feet at 811 Main, bringing the firm's total footprint in the tower to 103,336 square feet. CBRE represented the firm in that deal. The area in the new filing closely matches the size of that expansion, though the leasing announcement did not name the floor.