Microsoft Seeks Air Permit for Engines at $700M Medina County Data Center Campus

A Nov. 16 state registration covers Microsoft's SAT 9394 site on County Road 381, where state records list two $350 million single-story data centers.
Microsoft Corp. filed a new air permit-by-rule registration with the Texas Commission on Environmental Quality on Nov. 16, 2026, for a data center site it calls SAT 9394 on County Road 381 in Medina County, west of San Antonio. Texas Department of Licensing and Regulation records list two Microsoft data centers on that road, SAT93 and SAT94, each with an estimated construction cost of $350 million, or $700 million combined.
TCEQ records show the filing as registration 185961, project 417452, with a status of pending. The agency received the $450 fee on Nov. 16, and the file reached a review engineer on Nov. 17. The registration places the site north of Potranco Road on the west side of County Road 381, about 2.4 miles south of County Road 471. TCEQ's Central Registry lists the site's primary business as a data center, with San Antonio as the nearest city.
The registration claims two state permits by rule, which are standing air authorizations for common equipment that meets set conditions. The first, Rule 106.511, covers internal combustion engines and gas turbines that drive compressors, electric generator sets and water pumps used only for portable, emergency or standby service, according to TCEQ. The second, Rule 106.472, covers loading and unloading equipment and storage tanks for listed liquids. TCEQ's guidance says neither rule requires a registration or fee by itself, but Microsoft chose to register under both. The public summary does not list the number or size of the units.
Checking your membership…