Final Miller Road 2 Change Order Would Add $549K and 267 Days

Houston skyline, shown for Harris County context
Houston / Harris County location reference; not the construction site.

A final change order would lift Mar-Con Services' Precinct 1 contract to about $8.03 million, citing a hurricane, lime testing, extra fill and guardrail conflicts.

Harris County is asking Commissioners Court to approve a final change order adding $548,921.20 and 267 calendar days to Mar-Con Services LLC's contract to rebuild Miller Road 2 between Wallisville Road and US 90 in Precinct 1. The change order was up for a vote at the court's Nov. 19, 2026 meeting, as item 12, and the county had not posted the result at the time of writing.

According to the change order, dated Oct. 12, 2026, the change would raise the contract from its original $7,480,591.21 to $8,029,512.41, an increase of about 7%. No earlier changes had been approved. The work rebuilt the road from asphalt to concrete pavement. The document sets substantial completion at Feb. 27, 2026, and says delay damages apply after that date.

Most of the time comes from one item. A 250-day extension covers project delays the county attributes to control point determination, a hurricane, the time needed for lime testing, extra borrow material, meaning fill brought in from off site, and guardrail conflicts. A further 17 days cover a guardrail fix near Kimberlee Street, where the guardrail had been designed on top of a gas line, and added 5-inch slope paving.