Sentinel Halts Deepwater Construction Plans for $2.1 Billion Texas GulfLink Oil Export Port

Texas GulfLink offshore terminal rendering

The Dallas developer plans a Supreme Court petition after an appeals court vacated the federal approval, while onshore tank work continues at Jones Creek near Freeport.

Sentinel Midstream says it will not begin deepwater construction on its $2.1 billion Texas GulfLink crude oil export terminal off Brazoria County under current regulatory conditions, and it plans to ask the U.S. Supreme Court to review a federal appeals ruling that vacated the project's approval. In a court filing, the Dallas company acknowledged that the ruling exposes its deepwater port license to possible suspension or revocation and could block offshore construction, while site improvements and preparations for tank construction continue at its onshore terminal at Jones Creek near Freeport.

The 5th U.S. Circuit Court of Appeals ruled Aug. 12, 2026, that the U.S. Maritime Administration (MARAD) broke the Deepwater Port Act when it approved Texas GulfLink's license application on Feb. 14, 2025. A three-judge panel, with Judge Edith Brown Clement writing, granted a petition from Citizens for Clean Air & Clean Water in Brazoria County, known as Better Brazoria, vacated MARAD's record of decision and sent the matter back to the agency. The court issued its mandate, the order that puts the ruling into effect, on Oct. 30, 2026.

The case turned on a narrow rule. The Deepwater Port Act allows only one deepwater port in each "application area," the zone MARAD draws around a proposed port when it publishes notice of an application. Notices for two rival Freeport projects in March 2019, the Sea Port Oil Terminal (SPOT) and Texas COLT, included a strip 0.25 nautical miles wide on either side of their pipelines, but MARAD's June 2019 notice for Texas GulfLink covered only a circle 3.5 nautical miles wide around its platform and left the pipeline out.