Construction Under Way on Nearly $100 Million Hotel and Convention Center in Roanoke

Rendering of The Cade hotel and convention center in Roanoke

Brasfield & Gorrie is building The Cade Hotel, a five-story, 205-room Hilton hotel with more than 11,300 square feet of meeting space and a city-owned convention center in downtown Roanoke, with completion targeted for fall 2028.

Construction is under way on The Cade Hotel and convention center in downtown Roanoke, a project of nearly $100 million that will bring a five-story, 205-room hotel operated under Hilton to a site at 600 S. Oak St., just east of Roanoke City Hall. The city will own the convention center and lease land to the hotel operator.

The schedule calls for the structural frame to be completed in July 2027, the building shell in November 2027 and masonry in January 2028, with the project finished in fall 2028. A state filing registered in March lists a construction window from July 1, 2026, to May 1, 2028.