Core Scientific Plans $1.3 Billion Data Center Near Quinlan in Hunt County

Core Scientific’s existing Denton facility, shown as a company reference rather than the Hunt County site
Core Scientific’s Denton facility, shown for reference. Image: Core Scientific.

A $1.3 billion building registration adds detail to Core Scientific’s Hunt County campus, where construction is already reported and initial AMD customer delivery is targeted for the first half of 2028.

Core Scientific has registered a $1.3 billion data center building near Quinlan in Hunt County, adding a defined construction scope to a campus it acquired for $232.5 million in May. The November 13 state filing covers 341,326 square feet of core-and-shell space, together with site and infrastructure improvements at 4852 County Road 3507.

The filing lists November 24, 2026, as the start of its registered construction scope and September 4, 2028, as completion. Those dates sit alongside an earlier campus milestone: Core Scientific reported in September that construction had already commenced and long-lead equipment had been ordered. The new record should therefore be read as a building-package schedule, rather than the first evidence of activity on the land.

Hunt is also part of Core Scientific’s contracted expansion for AMD. The company’s November investor presentation identifies approximately 110 megawatts of leased customer power at the site, with initial delivery targeted for the first half of 2028. Additional reserved capacity creates a longer development opportunity, although it is separate from the first committed customer deployment.