Cottle County Approves Incentives for $1.1 Billion Data Center and Power Project

Aerial ranch photograph accompanying Project Matter coverage, showing existing buildings, paddocks and access roads

Aetheris’s Project Matter advances with an approved reinvestment zone and tax agreement for a 96MW data center and 180MW gas plant near Paducah. The published agreement sets out phased incentives, county payments and delivery milestones.

Cottle County commissioners voted unanimously on November 9 to approve a reinvestment zone and property tax abatement for Project Matter, Aetheris’s proposed data center and independent power facility east of Paducah. The project pairs 96 megawatts of critical IT capacity with a proposed 180-megawatt gas plant on ranch land off U.S. Highway 70.

The county’s hearing notice estimated approximately $1.113 billion in improvements, comprising $912 million for the data center and approximately $201.1 million for power production. The applicant is RS 70 Land Holdings, LLC, the Aetheris entity identified in the project’s community letters. Farmland Reserve Inc. and Paducah 324, LLC are the listed landowners.

The approval establishes local incentives rather than a completed construction start. The county has now published the agreement, which provides more precise terms than the earlier hearing coverage: a ten-year abatement for each phase, defined annual payments and an initial operating deadline in December 2029.

County agreement clarifies the land and schedule

Earlier project materials described approximately 4,252 acres, including up to 3,710 acres leased from Farmland Reserve and roughly 542 acres from another owner. The signed agreement defines the reinvestment zone as approximately 4,239.32 acres, and its map identifies a 13-acre exclusion. The initial development parcels total approximately 729 acres. These figures describe different boundaries and should not be treated as the footprint of a single building.

The agreement anticipates construction of the first data center beginning by the first quarter of 2027 and requires commercial operations by December 31, 2029. It allows a one-year extension through a $750,000 payment and written notice before or during 2029. Aetheris’s earlier website forecast of a fall-2026 start and approximately 18 months of construction remains an earlier developer estimate; it does not establish that work has begun.

Project Matter is on the historic Triangle Ranch east of Paducah. Farmland Reserve is a nonprofit owned by The Church of Jesus Christ of Latter-day Saints, while Aetheris is the project developer. AgReserves has said Aetheris is not affiliated with Farmland Reserve or the church and is responsible for the development. The wider ranch is expected to continue its agricultural use outside the leased project land.

What the county receives

The agreement grants a 100% abatement of eligible county property taxes for ten full calendar years per phase, subject to its conditions. Existing base-year property value and ineligible property remain taxable. Aetheris’s October 19 community letter also states that school district and groundwater district taxes are not abated.

In return, the initial phase carries a minimum annual payment in lieu of taxes of $2,500,080 before any applicable contractual credit. That calculation uses 180MW of electrical generation and 96MW of critical IT capacity. Additional operating capacity can increase payments. A separate $1.5 million acceleration payment is due within 90 days of the agreement’s effective date; that payment deadline is not evidence of a physical groundbreaking.

The document also provides for $1.957 million in first-year community benefit payments under an approved recipient schedule. The developer has proposed support for emergency services, roads, the library, the cemetery, education and other local organizations. These contributions are separate from the estimated construction and equipment investment.

Power, water and local impacts

The proposed power facilities include gas turbine generation, a substation and battery storage. Aetheris describes an islanded arrangement intended to serve the data center without drawing electricity from the local grid. The 180MW generating capacity and 96MW IT load measure different parts of the project and should not be combined into a larger data center capacity figure.

In its October 19 letter, Aetheris committed to sourcing water for construction, startup and operations outside Cottle County. That letter describes an approximately 400,000-gallon initial fill for closed-loop cooling and 20,000–25,000 gallons of annual makeup water, with potable water also brought in. Those cooling figures differ from the website’s older estimate of approximately 500,000 gallons of annual use; the outside supply source has not been publicly identified in the reviewed material.

The developer has said a Phase 1 Environmental Site Assessment is complete and has outlined noise controls, downward outdoor lighting, on-site truck staging and washing, and coordination of construction traffic. Residents at the hearing raised concerns about neighboring land, rural character and accountability, while supporters pointed to potential support for schools, public services and employment.

Construction and employment milestones to follow

The project website forecasts 600–800 construction jobs. Aetheris’s November 2 letter describes an initial operating workforce of 40–50 full-time and part-time positions, with more roles possible in later phases. These are developer forecasts, not a count of workers already employed on site.

The published agreement requires a construction commencement certificate within 30 days of the start of each data center project. That record, confirmed site activity, power-facility permits and named construction appointments will provide stronger evidence of delivery than the incentive approval alone. The general contractor, power EPC contractor and end user have not been publicly identified in the reviewed documents.

Explore Project Insights

Follow this project’s updates, construction milestones and researched contractor information in its dedicated Project Insight. Explore the profile for deeper coverage and membership access.

Explore project insights →