Project News / Water
SAWS Replaces Century-Old Hildebrand Water Mains as Businesses Seek Relief From Closures

Three weeks into a five-month project to replace aging pipe under East Hildebrand Avenue, District 1 Councilwoman Sukh Kaur brought utility and city officials together with business owners who say closures have cut their traffic.
San Antonio Water System is replacing water mains on East Hildebrand Avenue that date to the early 1900s, and nearby businesses say the road closures that came with the work have sharply reduced their customers. On Nov. 16, 2026, District 1 Councilwoman Sukh Kaur hosted a meeting with SAWS, VIA Metropolitan Transit, city staff and business owners along the corridor to look for ways to reduce the impact.
The work is part of SAWS job 23-4005, the 2023 Water Main Replacement Project 4. On East Hildebrand, crews are replacing about 4,600 feet of water main on Hildebrand Avenue and Old Hildebrand Avenue between McCullough Avenue and Devine Road. SAWS says the existing mains have had frequent breaks. The utility has said the pipes were installed in the early part of the 1900s and are about 100 years old or more. They are being replaced with high-density polyethylene pipe that SAWS says is designed for the area's difficult soil conditions and should last more than 100 years.
The SAWS board approved the project on Sept. 1, 2026. SAWS estimates the budget at $11.3 million for all three sites in Project 4. The second site covers about 8,500 feet of main on Camden Street, from Seymour Street to North St. Mary's Street, and on East Euclid Avenue, from North Main Avenue to east of McCullough Avenue. Construction there is expected to begin in about January 2027. Bid documents for Project 4 called for about 6,174 feet of 8-inch, 2,285 feet of 12-inch, 1,526 feet of 16-inch and 2,927 feet of 20-inch water main by open cut, plus casing installed by pipe jacking and street pavement repair. Bids were due June 16, 2026.
Checking your membership…