Harris County Flood Control Moves T.C. Jester Basin in Klein to Next Phase

Work on two more compartments of the 1,200-acre-foot Cypress Creek detention project is set to begin by the end of 2026.
The Harris County Flood Control District is preparing to start the next phase of the T.C. Jester Stormwater Detention Basin in Klein, a multi-compartment project that will hold about 1,200 acre-feet of stormwater in the Cypress Creek watershed when complete.
Phase 1B, which began construction in March 2026, is scheduled to finish in March 2027, according to the district. Phase 2, covering compartments 1A and 2, is set to begin before the end of 2026 and be completed in April 2027. Phase 3, the west compartment, is expected to begin in July 2027 and finish in 2028.