Project News / Infrastructure
Texas A&M Approves $14.2 Million Water System for RELLIS Campus

Regents approved a deep well, pipeline, cooling tower and storage tank to replace a water system built for a former Army airfield.
The Texas A&M University System Board of Regents on Nov. 12 approved a new water well and storage system for the Texas A&M-RELLIS campus in Bryan, appropriating $14.2 million for the project.
The system is sized to meet about 15 to 20 years of projected demand as research, teaching and industry work on the campus grows, according to the A&M System. Construction is scheduled to begin in December and be completed in March 2028.
Campus water infrastructure
The project is the third piece of the $205.5 million Texas A&M Semiconductor Institute project cleared for construction this year.
Well, pipeline and storage
The campus still depends on the water system and elevated storage tank built for the Army airfield that once occupied the site, and demand has outgrown that system, according to the A&M System.
The new well will be drilled to a depth of about 3,200 feet. It will be capable of pumping up to 2,800 gallons per minute and producing up to 1,934 acre-feet of water per year, or about 630 million gallons.
A 16-inch pipeline running about 1.6 miles will carry the water from the well to a new cooling tower and a 500,000-gallon ground storage tank. The ground storage tank will in turn feed the 1-million-gallon water tower that regents approved in September.
"Every one of those labs and classrooms needs water," said Board Chairman Robert Albritton. "This board would rather build for the next 20 years today than keep patching a system built for an Army airfield."
"Nobody tours a campus to see the well," said Chancellor Glenn Hegar. "But every lab, classroom and training center out there depends on it."
Hegar added, "Getting this right now means our students and researchers at RELLIS have room to grow for the next 20 years."
September water tower approval
Regents approved the new elevated water tower on Sept. 3. The 1-million-gallon tower is more than triple the capacity of the existing 300,000-gallon tower that served the former military airfield. The A&M System said the existing tower provides about 51 to 55 pounds per square inch of pressure, which is not enough for newer facilities and planned growth, and that new buildings have required separate pumps for fire protection and irrigation.
The water tower carries a total cost of about $11.755 million, including a new appropriation of about $10.58 million approved in September and about $1.18 million appropriated earlier. That tower is scheduled to begin construction in September 2026 and reach substantial completion in March 2028. At the time of the September approval, the A&M System said a separate water well infrastructure phase was expected to return to the board for construction approval later this year.
Semiconductor Institute
The Texas A&M Semiconductor Institute is planned as a national shared-use facility for semiconductor materials, specialized tools and domestic chip fabrication. Regents approved an increased total budget of $205.5 million for the institute's infrastructure and equipment project in February 2026, including about $177.95 million for the building and storm drainage.
Construction of the institute building began in March 2026, with substantial completion expected in January 2028 and occupancy in May 2028, according to the A&M System.
The institute project is funded with $157.4 million in state general revenue and $48.1 million in Permanent University Fund bond proceeds, according to the A&M System.