JCB Plans $8M Dealership Near $500 Million Plant in San Antonio

JCB San Antonio manufacturing plant rendering

A new 24,000-square-foot Boss JCB dealership is planned at 13806 State Highway 16 South, with construction scheduled to begin in November.

JCB Texas LLC plans an $8 million dealership at 13806 State Highway 16 South in San Antonio. The approximately 24,000-square-foot building is registered with the state, with RVK Architecture as the design firm.

The filed schedule calls for construction to begin November 16, 2026, and finish January 31, 2028.

The dealership comes as JCB prepares to begin production at its separate $500 million, approximately 1 million-square-foot manufacturing plant. That facility has received a temporary certificate of occupancy, with equipment testing and production preparations underway.

Factory production is targeted for the first quarter of 2027, followed by a planned April grand opening. JCB expects the manufacturing operation to employ approximately 1,500 workers.

Overview:

  • Project: Boss JCB Dealership
  • Owner: JCB Texas LLC
  • Location: 13806 State Highway 16 South, San Antonio, Texas
  • Sector: Construction equipment / dealership
  • Estimated Construction Cost: $8 million
  • Size: Approximately 24,000 square feet
  • Architect: RVK Architecture
  • Status: Registered; construction planned
  • Filed Start: November 16, 2026
  • Filed Completion: January 31, 2028
  • Related Development: Separate $500 million JCB manufacturing plant
  • Factory Production Target: First quarter of 2027