Commercial · Project profile

AT&T Stadium

By Elena Castillo

City of Arlington / Dallas Cowboys · Arlington

$1.15B original build · 3.1M SFOperational · opened 2009Updated October 3, 2026
Exterior of AT&T Stadium in Arlington
AT&T Stadium photograph: Manhattan Construction Company.

The construction story behind the Cowboys’ home: its original delivery team, retractable roof, mechanical systems and long-term reinvestment. Full profile free to read.

Project overview

AT&T Stadium brought the Dallas Cowboys to Arlington in 2009 after a construction program that began in April 2006. The approximately $1.15 billion original development combined an enclosed seating bowl, an operable roof, large moving end-zone doors and the infrastructure needed to serve football, concerts and other major events.

HKS describes a 3.1-million-square-foot venue on a 150-acre site. Manhattan Construction led delivery, with Rayco Construction and 3i Construction participating in the construction management team. Walter P Moore provided structural engineering. This free profile follows the original build and the stadium’s continuing life as an operating asset; historic contractors are not automatically the team for later upgrades.

Latest updates

Construction timeline, from announcement through delivery. Filed dates and future targets are labeled separately from confirmed events. Reviewed October 3, 2026.

  1. April 10, 2006

    Original construction

    Ground broken in Arlington

    The Cowboys’ official chronology records the start of construction for the stadium that would replace the team’s Irving home.

  2. May 27, 2009

    Completed milestone

    Ribbon cutting held

    The stadium was unveiled with the opening of its glass end-zone doors. This ceremonial milestone preceded the first public entertainment event.

  3. June 6, 2009

    Operational opening

    First event welcomes the public

    A George Strait-led concert opened the venue’s event calendar ahead of its first football season.

  4. 2010–2019

    Project recognition

    Design and delivery receive recognition

    Recognition includes the 2010 Sports Facility of the Year and 2019 Facility of the Decade awards listed by HKS, alongside structural and construction awards documented by the project team.

  5. April 2026

    Approved agreement

    Lease-extension agreement approved

    Arlington approved an agreement extending the Cowboys’ lease through 2055, with long-term maintenance, operations and improvement commitments. It is not a single newly awarded construction package.

Who built the stadium

The original construction depended on coordination between the management team and specialist trades. JMEG’s electrical role is documented in a contemporaneous interview with its stadium superintendent. TDIndustries identifies its own scope as design-assist HVAC, plumbing and hydronics.

  • Construction management: Manhattan Construction, Rayco Construction and 3i Construction
  • Architecture: HKS
  • Structural engineering: Walter P Moore
  • Electrical construction: JMEG
  • Mechanical and plumbing: TDIndustries
  • Roof mechanization design: Uni-Systems

A roof that shaped the whole structure

Walter P Moore describes two 1,225-foot arched box trusses supporting a roof structure containing 14,100 tons of structural steel. The retractable roof panels operate in about 12 minutes; the large end-zone doors have a separate opening cycle.

The engineering challenge extended into the foundations and seating bowl. The field sits approximately 50 feet below street level, while concrete framing and precast seating units carry the spectator areas. The roof, suspended video board and moving elements had to be coordinated as one structural system.

For construction teams, the lesson is the relationship between erection sequencing and permanent design. Access for lifting, temporary stability and the installation of services all need to work with the final structure, rather than being planned independently.

The mechanical plant behind the experience

TDIndustries reports 11,000 tons of central-plant cooling capacity, 60 miles of piping and 3.2 million pounds of sheet metal. Its project account also lists 13,600 plumbing fixtures and 2,600 food-service equipment connections.

The company fabricated ductwork and plumbing at its Dallas shop and developed a bridge platform for installing ductwork in the bowl. These methods show why off-site preparation and installation access mattered on a venue with a large column-free interior.

Those quantities are TDIndustries’ published project figures. They describe its historical work and should not be treated as the scope of a current replacement or maintenance contract.

Capacity depends on the event

Seating and attendance figures describe different configurations. Manhattan and Walter P Moore describe an approximately 80,000-person venue expandable to 100,000, while HKS lists 70,000 seats with expansion to 100,000. TDIndustries cites accommodation for up to 112,000 people.

This profile uses approximately 80,000 as the general capacity reference and treats larger figures as event-dependent. The highest accommodation figure is not the permanent seated capacity for every Cowboys game.

The next chapter is long-term reinvestment

Under the April 2026 agreement, the Cowboys committed at least $750 million for maintenance, operations and improvements through the extended lease term. Arlington’s contribution is up to $273 million in net present value over 20 years.

These commitments combine different activities and time periods; adding them together as an immediate construction award would be misleading. Individual improvement packages need their own scope, design team and procurement record.

Arlington cites an HR&A Advisors analysis estimating roughly $324 million in annual economic impact from current stadium operations. That is an economic-model estimate for Arlington, rather than stadium revenue, construction spending or a direct payroll total.

What to watch next

  • Defined improvement packages under the lease-extension agreement.
  • Confirmed procurement and team appointments for future work.
  • How upgrades are phased around the stadium’s operating calendar.

Explore other projects

Official Terafab project visualization
Image: Tesla / SpaceX — Terafab project visualization

Members · Project Insights

Terafab

100M+ sq ft planned

Tesla and SpaceX’s planned chip-making complex would combine logic, memory and advanced packaging at an extraordinary scale.

Read project insight
Rendering of Lilly’s planned manufacturing campus at Generation Park
Lilly Houston campus rendering, published by McCord / Generation Park.

Members · Project Insights

Eli Lilly Houston

$6.5B manufacturing campus

A pharmaceutical manufacturing campus for active ingredients, with a multiyear construction and commissioning program at Generation Park.

Read project insight
Aerial view of Project Llano in Claude
Goodnight / Project Llano campus: Google Maps.

Members · Project Insights

Google / Crusoe — Project Llano

1,100+ acres · 1GW+ planned

A six-building data center campus with phased Google handovers targeted for 2027. Members can explore the contractor map and delivery updates.

Read project insight
Project Matador construction progress photographs from August 12, 2026
Image: Fermi America — site progress, August 12, 2026

Members · Project Insights

Project Matador

17GW planned campus

Fermi America’s planned 17GW power and data-center campus in the Panhandle, described by the developer as the world’s largest private power and compute campus.

Read project insight
Conceptual illustration of a data center campus in South Texas
Concept illustration — not the actual campus design or a site photograph.

Members · Project Insights

Fluidstack $4B Data Center

$4B phase one · up to 1.5GW planned

A campus spanning more than 1,100 acres between Valley International Airport and the Port of Harlingen. Members can explore the Phase 1 scope, reported project team and construction timeline.

Read project insight
Architectural rendering of the George R. Brown convention center expansion
Project rendering supplied by publisher.

Members · Project Insights

$2 Billion George R. Brown Convention Center Transformation

$2B transformation · 700,000-SF first phase

A multiyear transformation of Houston’s convention campus and surrounding district. GRB South targets a May 2028 opening, with the full transformation anticipated by 2038. Members can explore the development team, construction packages and timeline.

Read project insight
Aerial construction view of the Abilene data-center campus supplied by the publisher
Image supplied by publisher; capture date not provided.

Free · Project Insights

Project Stargate - Abilene Data Center

8 buildings · approximately 4M SF · 1.2 GW planned

Abilene is the flagship campus associated with the $500 billion national Stargate initiative. The eight-building core combines data halls, cooling and power infrastructure. Explore the project team, construction packages and full delivery timeline in this free Project Insight.

Read project insight
Rendering of Texas A&M Meat Science and Technology Center
Project rendering: Texas A&M University System.

Members · Project Insights

Texas A&M $133.4M Meat Science & Technology Center

$133.4M · approximately 85,600 SF

A research and teaching facility on West Campus combining laboratories, processing spaces and public-facing facilities. Members can explore the delivery team, utility package and construction timeline.

Read project insight
Texas A&M Semiconductor Institute project rendering
Rendering: Texas A&M University System.

Free · Project Insights

Texas A&M Semiconductor Institute

$205.5M program · approximately 73,000 SF

A specialist research and training facility with cleanrooms, advanced laboratories and major supporting utilities. Explore the complete project team and delivery schedule in this free Project Insight.

Read project insight
Oak Hill Parkway opening ceremony
Opening ceremony: Fluor.

Free · Project Insights

Completed

$677M Oak Hill Parkway

$677M · approximately seven miles

Explore the completed roadway, delivery team and construction timeline in this free Project Insight. Final paving, striping and landscaping continue through late 2026.

Read project insight
Completed buildings at Kyle Technology Park
Photo: Cadence McShane Construction.

Free · Project Insights

Kyle Technology Park

75,000 SF completed · 300,000 SF planned

The completed 75,000-SF first phase includes three buildings and supporting infrastructure within TIG Real Estate Services’ planned 41-acre business park.

Read project insight
Warehouse exterior with loading docks, office entrance and landscaped frontage
Image supplied by publisher.

Free · Project Insights

Intermodal Logistics Center West

$750M campus · 1,007,817-SF first building

Crossland is delivering the 1,007,817-SF first building at Intermodal Logistics Center West, with CBRE marketing Q1 2027 delivery within the planned $750 million campus.

Read project insight
City of Waco Barron’s Branch groundbreaking graphic with district rendering
Image: City of Waco / Waco Downtown Redevelopment. District rendering.

Free · Project Insights

Barron’s Branch District

$184M agreement · approximately 30 acres

The 30-acre downtown district is moving into construction under Hunt Real Estate & Infrastructure, with roads, utilities, public spaces and creek reconstruction targeted for completion in April 2029.

Read project insight
Power Electronics Houston groundbreaking ceremony
Photo: Power Electronics — Houston groundbreaking.

Free · Project Insights

Power Electronics Houston Manufacturing Campus

850,000 SF announced · up to 40GW annual production

Freehill’s Fairbanks Landing Phase I adds developer and design-team detail to Power Electronics’ Houston campus, planned for up to 40GW of annual production capacity.

Read project insight
Rendering of Austin-Bergstrom’s Concourse M passenger entrance
Rendering: Austin-Bergstrom International Airport / City of Austin.

Free · Project Insights

Austin Airport — Concourse M

Six gates · approximately 37,000 SF

Hensel Phelps is the prime contractor and Stantec/Fentress leads design for the satellite concourse, with passenger opening targeted as early as 2028.

Read project insight
Concept illustration of a natural-gas power campus, not the final Project Star design
Concept illustration — not the final Project Star design.

Members · Project Insights

Project Star — Encinal

$22.3B · 6.47GW generation · 5GW adjacent data campus

Track the development partners, permitting milestones and phased delivery of the proposed Encinal power campus serving an adjacent digital infrastructure development.

Read project insight
Saronic rendering of the planned Port Alpha shipyard
Port Alpha rendering: Saronic, published by WorkBoat.

Members · Project Insights

Saronic Port Alpha Shipyard

$3B+ · 835-acre initial site · 1.2M SF enclosed production

An initial 835-acre shipbuilding campus at the Port of Brownsville with production buildings, deepwater quay and room for future expansion. Members can explore the construction team and delivery milestones.

Read project insight
Rendering of JCB’s San Antonio manufacturing campus
JCB plant rendering supplied by publisher.

Members · Project Insights

JCB San Antonio Manufacturing Campus

$500M · nearly 1M SF · 400 acres

A manufacturing campus on Palo Alto Road planned for telehandlers, scissor lifts and aerial-access equipment. Members can explore the delivery team, construction scope and phased handover schedule.

Read project insight
Equinix logo
Equinix logo supplied by publisher.

Members · Project Insights

Equinix DA12

$836.5M filed work · 372,517 SF · 67MW planned

A West Dallas data-center development with separate core-building and interior fit-out packages. Members can explore the contractor map, construction scope and filed delivery timeline.

Read project insight

Members · Project Insights

MacGregor Park Transformation

$75M program · $50M filed construction

A two-phase renewal of courts, recreation buildings, trails and public spaces at the historic Third Ward park. Members can explore the delivery team and construction timeline.

Read project insight
TJJD rendering of the proposed Brazoria County facility
Rendering: Texas Juvenile Justice Department.

Members · Project Insights

Brazoria County Juvenile Justice Facility

104 beds · part of $304M two-facility program

A new secure state facility in Rosharon, paired with a separate Ellis County development. Members can explore the project team, shared funding context and dated construction milestones.

Read project insight
Aerial photograph of the Hutto data-center campus supplied by the publisher
Hutto campus photograph supplied by the publisher; existing campus buildings, not the proposed Building 4.

Members · Project Insights

Skybox / Prologis — Hutto PowerCampus Austin

160-acre marketed campus · $550M Building 4 filing

A phased Skybox–Prologis data-center campus in Hutto. Members can explore the campus contractor, building-specific scope, power-capacity distinctions and delivery timeline.

Read project insight
Houston Texans stadium exterior at night, pictured with NRG Stadium signage
Image supplied by publisher; photograph shows the stadium under its former NRG name.

Free · Project Insights

Reliant Stadium

1.9M SF · NFL’s first retractable-roof stadium

Explore the Texans’ stadium from its 2000 groundbreaking to its original contractor team, cooling systems and later roof renewal. Full profile free to read.

Read project insight