Semi-Conductor & Manufacturing · Project profile

Power Electronics Houston Manufacturing Campus

By Sofia Ramirez

Power Electronics / Freehill Development · Houston

850,000 SF announced · up to 40GW annual productionGroundbreaking heldUpdated November 22, 2026
Power Electronics Houston groundbreaking ceremony
Photo: Power Electronics — Houston groundbreaking.

Freehill’s Fairbanks Landing Phase I adds developer and design-team detail to Power Electronics’ Houston campus, planned for up to 40GW of annual production capacity.

Project overview

Power Electronics announced the groundbreaking of its Houston manufacturing campus on September 24. The planned 850,000-square-foot development combines production and logistics with engineering, training and corporate functions.

The company expects the campus to serve demand from solar, energy storage, data centers and electrical infrastructure. Its 40GW figure measures annual equipment production capacity, not electricity generated at the site.

September 28 reporting on Fairbanks Landing identifies Freehill as the developer of the first-phase build-to-suit for Power Electronics, with delivery targeted for the third quarter of 2027.

Latest updates

Construction timeline, from announcement through delivery. Filed dates and future targets are labeled separately from confirmed events. Reviewed November 22, 2026.

  1. September 24, 2026

    Confirmed milestone

    Manufacturer breaks ground

    Power Electronics announces its Houston campus at 9220 Fairbanks North Houston Road.

  2. September 28, 2026

    Development update

    Build-to-suit developer and phase defined

    Fairbanks Landing reporting identifies Freehill’s 809,220-SF first phase for Power Electronics and a Q3 2027 delivery target.

  3. October 9, 2026

    Procurement deadline

    Traffic-signal bids due

    Quiddity’s solicitation covers supporting traffic-signal work serving Fairbanks Landing. This is a bid deadline, not a contract award.

  4. Q3 2027 target

    Target

    Phase I building delivery

    Target for the developer’s first phase; manufacturing commissioning and achievement of full production capacity are separate milestones.

Manufacturing and Building Systems

The campus is planned to accommodate logistics, production, electronics manufacturing, research, training and offices. Bringing these uses together creates different requirements for production space and occupied support areas.

TCH scope assessment: likely construction interfaces include foundations and industrial slabs, structural frames, loading facilities, electrical services, ventilation, fire protection and automation. Production-line installation and acceptance testing would need to be coordinated with the building handover.

Fairbanks Landing and the delivery team

Method Architecture identifies Freehill Development, Quiddity Engineering and Pinnacle Structural Engineers on the Fairbanks Landing team. JLL handles transaction and leasing representation. The wider development is planned at 1.64 million SF across four buildings.

The first phase totals 809,220 SF across two buildings. That developer figure differs from Power Electronics’ approximately 850,000-SF campus announcement, which describes buildings of roughly 150,000 SF and 700,000 SF. The figures reflect their respective published descriptions and should not be combined into a larger construction total.

Infrastructure work and remaining appointments

A Quiddity-led solicitation covers traffic-signal modifications serving Fairbanks Landing, with bids due October 9, 2026. This is a supporting infrastructure package, separate from the manufacturing buildings.

A general contractor and electrical, mechanical and process-equipment contractors have not been publicly confirmed in the information reviewed. The manufacturer has not disclosed its total campus capital cost. Building delivery in Q3 2027 is distinct from the date full production capacity is achieved.