Austin Airport — Concourse M

By Ryan Mitchell

City of Austin / Austin-Bergstrom International Airport · Austin

Six gates · approximately 37,000 SFGroundbreaking held · construction due to beginUpdated November 24, 2026
Rendering of Austin-Bergstrom’s Concourse M passenger entrance
Rendering: Austin-Bergstrom International Airport / City of Austin.

Hensel Phelps is the prime contractor and Stantec/Fentress leads design for the satellite concourse, with passenger opening targeted as early as 2028.

Project overview

Austin-Bergstrom International Airport held the official groundbreaking for Concourse M on September 29. The airport described it as a ceremonial milestone, with construction to begin soon, within the multibillion-dollar Journey With AUS program.

The airport’s latest announcement names Hensel Phelps as prime contractor and Stantec/Fentress JV as design lead. The approximately 37,000-SF facility will provide four contact gates and two walk-out positions for narrow-body aircraft.

Latest updates

Construction timeline, from announcement through delivery. Filed dates and future targets are labeled separately from confirmed events. Reviewed November 24, 2026.

  1. March 26, 2026

    Council approval

    Concessions lease authorized

    City Council authorizes the Star Concessions food-service and retail lease.

  2. Earlier state filing

    Filed schedule

    Filed construction schedule

    The filing recorded July 2026–October 2027 and approximately $60M. These are submitted dates and value, not evidence of actual field progress.

  3. September 29, 2026

    Confirmed milestone

    Official groundbreaking

    AUS holds the ceremony; its announcement says construction will begin soon. Hensel Phelps is prime contractor and Stantec/Fentress JV leads design.

  4. 2027 target

    Related project target

    Related maintenance ramp completion

    RS&H and Austin Bridge & Road are delivering the companion Maintenance Ramp Expansion, separate from Concourse M.

  5. As early as 2028

    Target

    Passenger opening

    Airport target for passenger operations after construction and operational readiness work.

  6. November 24, 2026

    Reported permit; editorial review

    Permit report added; opening target retained

    November 17 building-permit issuance is reported at $60M declared valuation. The state filing’s October 2027 construction target is separate from the airport’s passenger-opening target as early as 2028.

A Bridge During Airport Expansion

The west-airfield facility is designed for six narrowbody gates: four contact gates and two walkout positions. Passengers will connect with the Barbara Jordan Terminal by shuttle, making bus facilities and transfer arrangements part of the operational scope.

Concourse M is intended to preserve gate capacity during larger works. It is expected to transition to a cargo-related use later, giving the temporary passenger facility a potential longer-term role.

Updated opening target and earlier filing

The airport targets passenger opening as early as 2028. An earlier state filing described 38,224 SF, approximately $60 million in construction and a July 2026–October 2027 construction window. The latest announcement describes approximately 37,000 SF and does not restate the cost.

The September 29 ceremony is the confirmed groundbreaking milestone. The earlier filed dates remain a record of the submitted schedule rather than proof of actual construction progress. Passenger opening also requires operational readiness beyond building completion.

Delivery Team and Trade Interfaces

Electrical distribution, building services, communications, passenger systems and apron interfaces are relevant areas for following package-level developments. The reviewed airport documents do not provide a complete subcontractor roster.

Confirmed trade appointments and commissioning milestones will add useful detail as Hensel Phelps and the design team advance the facility toward passenger operations.

Maintenance Ramp Expansion

A companion Maintenance Ramp Expansion supports airport operations during the wider construction program. RS&H is planning that project and Austin Bridge & Road is constructing it, with completion targeted for 2027.

Those appointments apply to the maintenance ramp. Hensel Phelps and Stantec/Fentress remain the named prime contractor and design lead for Concourse M.

Passenger connections and amenities

Shuttles will run from Gate 13 in the Barbara Jordan Terminal. Concourse M supports operations during construction of the 26-gate Concourse B and Tunnel and remodeling of Concourse A.

Amenities include family and full-size restrooms, a nursing room, WiFi, pet relief and seating. Star Concessions will provide a coffee market, grab-and-go offerings and 24-hour vending under a lease authorized March 26, 2026.

Airport funding and ramp capacity

The companion ramp adds six aircraft parking positions and capacity for up to 18 diverted aircraft. Its FAA support exceeds $9 million through the AIG and AIP programs.

Both projects use airport revenues, reserves, federal grants and future airport revenue bonds, without local taxpayer funding. The ramp’s grant amount is separate from Concourse M’s earlier filed construction estimate.

Building-permit report and construction valuation

The November 24 briefing reports issuance of building permit 2026-084222 BP on November 17, with $60 million in declared construction valuation. This is a permit valuation, not a separate new $60 million contract award.

The state registration independently records 38,224 SF and the earlier July 24, 2026–October 24, 2027 submitted construction window. Passenger opening remains targeted as early as 2028 and depends on operational readiness as well as completion of the building.

Read the latest project coverage ↗