Austin’s $4.5B I-35 Overhaul Reaches Two-Year Construction Milestone

I-35 in Austin: photograph.
I-35 in Austin: photograph.

The eight-mile Capital Express Central program is advancing through separate bridge, roadway and drainage packages, with major work continuing toward 2033.

Austin’s I-35 Capital Express Central reconstruction has reached the two-year point since construction began in October 2024. The milestone concerns a long-running corridor program, not a newly awarded $4.5 billion contract.

The work extends roughly eight miles through central Austin. Its separate construction segments allow bridge replacement, drainage installation and roadway reconstruction to progress on different schedules while traffic continues using the corridor.

Project at a Glance

Program:
Approximately $4.5 billion
Corridor:
US 290 East to SH 71 / Ben White Boulevard
Length:
Approximately eight miles
Drainage package:
Two tunnels and a pump station

Checking your membership…

Browse researched project scopes, delivery teams and construction timelines.

Explore insights →

A corridor rebuilt in packages

TxDOT’s program includes removing the existing upper decks, lowering mainlanes and adding two non-tolled managed lanes in each direction. It also includes changes to cross-street connections and facilities for people walking and cycling.

The segment structure matters. The Martin Luther King Jr. Boulevard work, Lady Bird Lake works, drainage infrastructure, University segment and Downtown segment are not interchangeable measures of progress. Completion of one part does not establish that the whole corridor is ready.

Drainage is a major construction workstream

TxDOT describes the drainage segment as two tunnels, a pump station and access shafts. The shafts provide maintenance and operational access to infrastructure that will remain largely below ground.

The agency lists a mid-2025 construction start and anticipated completion in 2029, weather permitting. That schedule belongs to the drainage package. It should not be substituted for the completion date of the entire Central project.

Lowering a roadway makes stormwater management integral to the permanent design. The drainage works therefore support the future highway configuration rather than functioning as a separate cosmetic improvement. Underground progress may be less visible than a bridge demolition, but it remains a significant part of the delivery sequence.

Why the work continues toward 2033

The Lady Bird Lake segment is scheduled across 2025–2033, illustrating the longer horizon for major corridor works. TxDOT’s published schedules identify different windows for different segments, rather than a single uninterrupted construction operation.

For nearby businesses and travelers, the relevant information is the current segment notice and traffic arrangement. A program anniversary is useful context, but it does not replace location-specific closure information or establish that a particular bridge or access road has reopened.

What comes next

The useful construction indicators are progress on tunnel and pump-station installation, bridge works, roadway staging and changes between traffic phases. Future reports should identify the package, location and date of each milestone.

The next steps also need to be distinguished from new procurement. Work already under contract can advance significantly without generating a fresh award. Confirmed drainage-team details are available to members below; no unverified appointments have been added.

Keep reading

1.Carrier Plans $600M Fort Worth Manufacturing Facility2.Frisco Approves Up to $5M in Incentives for Toyota Stadium Hotel District3.TCEQ Disables Automated Permit Filing After Data-Center Dispute4.NextEra Advances 16.5GW Power Program With Two Projects in Texas5.Houston’s $2.6B Terminal B Transformation Reaches Major Opening Milestone6.Midland County Proposes $299M Water Infrastructure Programme7.$78M Artana at Brooks Opens With 349 San Antonio Apartments8.A&M–San Antonio Opens $55M Public Health and Education Building9.Sugar Land Reviews $39.2M Runway Reconstruction Contract10.Galveston Considers $15.4M Contract for 7.5-Million-Gallon Water Tank11.Advanced Manufacturer Takes 106,000-SF Leander Facility12.$57.7M, 1-Million-SF Industrial Shell Filed in Fort Worth13.Eight-Building Seguin Commerce Park Begins First Phase14.West Texas AI Campus Secures Integrated Water Infrastructure Package15.Scannell Plans $12M Cedar Park Commerce Industrial Building16.Pflugerville Plans 75,000-SF Defense Manufacturing Initiative17.Target Files $4.5M Austin Highway Store Renovation18.CBRE Makes $1 Billion Move Into Data Center Infrastructure19.$70 Million Texas Hospital Breaks Ground20.Elon Musk's Boring Company Prepares to Tunnel Under San Antonio21.Kinder Morgan Approves $4.7 Billion Pipeline Investment Program22.$610 Million South Texas Manufacturing Facility Reaches Major Construction Milestone23.3,500 Homes Planned Across 1,318-Acre Margaritaville Development in Texas City24.Amazon files $100M 1.2M SF Robotics factory in Austin25.Soluna and Applied Digital Plan 50MW AI Data Center Near Silverton26.TCEQ Says Data-Center Permit Pause Is in Place as Processing Dispute Continues27.Federal Government Asks Supreme Court to Lift Big Bend Construction Block28.S&B's Texas Megaproject Wins Construction Excellence Award29.UT San Antonio Explores San Pedro III as Downtown Housing Needs Grow30.H-E-B Files $23 Million Garland Store and Separate Fuel-Station Project31.VENU Closes $60 Million Financing Transaction for McKinney Amphitheater32.AtkinsRéalis Wins TxDOT Austin Traffic Management Contract