Soluna and Applied Digital Plan 50MW AI Data Center Near Silverton

Company logos: Soluna and Applied Digital.
Company logos: Soluna and Applied Digital.

A conditional joint-venture agreement advances Project Dorothy 3, while the intended tenant has signed only a nonbinding letter of intent.

Soluna Holdings and Applied Digital have agreed to form a company to develop a planned 50MW critical-IT data center at Project Dorothy 3 near Silverton. The October 21 announcement gives the proposal a defined ownership structure while leaving several material steps ahead of closing.

Applied Digital is expected to hold 51% and Soluna 49%. Soluna would contribute land and power-related assets, with Applied providing development capital. The announcement does not disclose a total construction value or identify a general contractor.

Project at a Glance

Planned IT capacity:
50MW
Ownership at closing:
Applied Digital 51%; Soluna 49%
Associated wind farm:
Briscoe Wind: 150MW
Closing target:
End of 2026; conditional

The power arrangement still needs definitive documents

Dorothy 3 is planned alongside the 150MW Briscoe Wind Farm and near Soluna’s existing Dorothy developments. The proposed initial phase is expected to use both wind-farm power and grid electricity, subject to final agreements.

The wind farm’s nameplate capacity and the data center’s critical IT load describe different things. They should not be added together or used to suggest that the planned building will operate exclusively on wind generation at all hours. The final power and operational arrangements remain important milestones.

A prospective tenant, rather than an executed lease

ChronoScale has signed a nonbinding letter of intent for the planned facility. A definitive lease still needs to be negotiated and executed. That distinction matters because a tenant indication of interest does not provide the same construction and financing certainty as a completed lease.

Closing conditions also include a Briscoe County tax abatement, title policies, corporate approvals and definitive operating and power agreements. The end-of-year closing target is therefore conditional; it is not an announced date for the building to become operational.

Construction scope to follow

The project could create demand for data-hall construction, cooling equipment, electrical distribution and associated site infrastructure. The announcement does not establish the selected systems, awarded trade packages or construction sequence, so these remain potential disciplines rather than confirmed procurement opportunities.

The next useful updates are the joint venture’s close, a binding tenant agreement, a defined construction budget and appointments to the delivery team. Those developments would help move Dorothy 3 from a conditional development agreement toward a more definite construction program.

Keep reading

1.Carrier Plans $600M Fort Worth Manufacturing Facility2.Frisco Approves Up to $5M in Incentives for Toyota Stadium Hotel District3.TCEQ Disables Automated Permit Filing After Data-Center Dispute4.NextEra Advances 16.5GW Power Program With Two Projects in Texas5.Houston’s $2.6B Terminal B Transformation Reaches Major Opening Milestone6.Midland County Proposes $299M Water Infrastructure Programme7.$78M Artana at Brooks Opens With 349 San Antonio Apartments8.A&M–San Antonio Opens $55M Public Health and Education Building9.Sugar Land Reviews $39.2M Runway Reconstruction Contract10.Galveston Considers $15.4M Contract for 7.5-Million-Gallon Water Tank11.Advanced Manufacturer Takes 106,000-SF Leander Facility12.$57.7M, 1-Million-SF Industrial Shell Filed in Fort Worth13.Eight-Building Seguin Commerce Park Begins First Phase14.West Texas AI Campus Secures Integrated Water Infrastructure Package15.Scannell Plans $12M Cedar Park Commerce Industrial Building16.Pflugerville Plans 75,000-SF Defense Manufacturing Initiative17.Target Files $4.5M Austin Highway Store Renovation18.CBRE Makes $1 Billion Move Into Data Center Infrastructure19.Austin’s $4.5B I-35 Overhaul Reaches Two-Year Construction Milestone20.$70 Million Texas Hospital Breaks Ground21.Elon Musk's Boring Company Prepares to Tunnel Under San Antonio22.Kinder Morgan Approves $4.7 Billion Pipeline Investment Program23.$610 Million South Texas Manufacturing Facility Reaches Major Construction Milestone24.3,500 Homes Planned Across 1,318-Acre Margaritaville Development in Texas City25.Amazon files $100M 1.2M SF Robotics factory in Austin26.TCEQ Says Data-Center Permit Pause Is in Place as Processing Dispute Continues27.Federal Government Asks Supreme Court to Lift Big Bend Construction Block28.S&B's Texas Megaproject Wins Construction Excellence Award29.UT San Antonio Explores San Pedro III as Downtown Housing Needs Grow30.H-E-B Files $23 Million Garland Store and Separate Fuel-Station Project31.VENU Closes $60 Million Financing Transaction for McKinney Amphitheater32.AtkinsRéalis Wins TxDOT Austin Traffic Management Contract